The center of the Delta Project
|
|
|
|
In fact Neeltje Jans is a special case on this site. Strictly
speaking it does not really meet two of the most important criteria that
I formulated on the introduction page under "But... what is an island?":
it is not permanently inhabited and it never was in the past, and
neither it can boast on a rich island tradition. And what's more, actually
it isn't even an island, as you can get there by car without any problem!
Yet I had no doubts when considering the question whether this former
sandbank in the Eastern Scheldt deserves a place on the site. The
reason is that since 1979 this small island houses the country's major information and exhibition center regarding the Delta Project.
There is no other place where you are presented such a comprehensive
overview of the making of the Zeeland delta area and the everlasting
struggle against the water, the leitmotiv that dominates its history.
The struggle that eventually has resulted in the realization of the Delta
Project.
In a certain way Neeltje Jans can be considered as the center of the Delta
Works. It owes its very existence to the Eastern Scheldt storm surge
barrier, which is commonly regarded as the pinnacle of this huge
project. Additionally, this little island was of vital importance for
the realization of the barrier and it is even an integral part of it as
well.
The information center has now evolved into a real theme park under the
name 'WaterLand Neeltje Jans', attracting over 300,000 visitors yearly
from all over the country and abroad. And right it is. In fact, a visit
to the islands of Zeeland should always start here, on Neeltje Jans. |
|
|
Nehalennia, once more
|
|
|
|
It's impossible to say how old Neeltje Jans exactly is. The only thing
we know is that the oldest map showing a sandbank with this name in the
mouth of the Eastern Scheldt estuary goes back to the year 1799. The French
cartographer who made this map named the sandbank 'Neeltje Jans' because
a ship of that name would have been wrecked here, but there are no other
sources confirming this story.
So, what was been here before 1799 is uncertain. We must realize that
the delta area is extremely dynamic and that its appearance has been
continuously changing over the years. Sandbanks formed spontaneously and
sometimes even developed into inhabited islands that -after some decades
or only after centuries- might be swallowed again by the water. For example,
by the end of the 16th century, at about the location of today's Neeltje
Jans, the little island of Orisant was situated. It was a sandbank with
some salt marshes that became diked in 1602 and then were leased out to
farmers for pasturing their cattle. However, the new island dwellers did
not hold out very long. After several dike breaches and subsequent
floods they were forced to give up the island and leave in 1639, after
which it disappeared under the sea forever.
|
|
|
Neeltje Jans
-
some figures
Length 3,5 km,
width max. 2.5 km, area approx.. 1.5 km²,
population 0.
|
|
|
Most sources agree that the name 'Neeltje Jans' is a common corruption
of Nehalennia, the Roman goddess that played a prominent role in this
area at the beginning of our era and who has already been discussed on
the Walcheren and Noord-Beveland pages. At two different locations, both
within a 25 km-range of the present island of Neeltje Jans, major finds
have been made that confirm the prominent position of this goddess. Near
Domburg, on the present island of Walcheren, the remains of a sanctuary
that was dedicated to Nehalennia were uncovered from below the sand of
the dunes by a heavy storm in 1647. And since 1970 dozens of altar
stones with the likeness of the goddess have been dredged up from the
waters of the Eastern Scheldt near the village of Colijnsplaat on the
present island of Noord-Beveland. These must originate from the
Nehalennia temple of the Roman settlement Ganuenta, that is mentioned in
ancient documents.
The character of Nehalennia is somewhat mysterious. Although the finds
mentioned indeed go back to the time that the Romans lived in this area
and often show inscriptions in Latin, some sources claim that the
worship of the goddess is much older and has its origin in the Celtic
culture. The Romans are assumed to have adopted the Nehalennia-cult and
embedded it in their own religious tradition, as also happened elsewhere
in the vast Roman Empire with indigenous mythology. Something similar
happened in later ages, when Christianity gained a firm foothold in this
area and remodeled the goddess Nehalennia seamlessly into the Holy
Virgin Mary.
It's for sure that with the Celts as well as the Romans Nehalennia was
the goddess of security and protection against the sea. As such she
became the patroness of the seamen, which explains her great popularity
in this area with a long tradition of overseas trade. At that time it
was common practice that the merchants, prior to a dangerous voyage
overseas, went to the sanctuary of the goddess to pray for a safe
passage. And if their prayers were answered they often gratefully
presented an altar stone to the temple after their return. It is this
kind of stones that were retrieved in large numbers from the bottom of
the Eastern Scheldt.
It is a striking circumstance that the little island of Neeltje Jans
that was named after Nehalennia has become the cradle of the Eastern
Scheldt storm surge barrier, the hydraulic wonder which since 1986
protects the population of a large part of Zeeland against the sea. So,
in a certain way the goddess of security -in a contemporary form- still
lives on! |
|
|
"This never again!"
|
|
|
|
The struggle against the water is the leitmotiv in the history of the
area of the Zeeland delta. The stories of storms and floods through the
ages are almost countless; the first documented report goes all the way
back to the year 838. In the 15th century there were the two St.
Elizabeth floods, in 1530 there was the notorious St. Felix flood ('Quade
Saterdach' or 'Bad Saturday') that completely swept the islands of
Noord-Beveland and Sint Philipsland away, and in 1532 as well as in 1570
there was a severe flood on All Saints Day (1st of November). It is just
a pick from a long series.
All those disasters caused great losses of lives and massive damage to
goods an chattels. It is obvious that every disaster was succeeded by
measures to prevent that such a thing would ever happen again: raising
and reinforcement of existing dikes, construction of new ones, dike
watch to detect the weak places at an earlier stage and better
cooperation and coordination in dike management and maintenance. Of
course this really did help, but yet there would always be a moment,
later in time, when it would go wrong again.
Like in the final night of January 1953, when a fatal combination of a
very heavy northwesterly storm (force 11 Beaufort) and spring tide
pushed up the waters in the funnel of the southern part of the North Sea
to a height that had never been measured before. The effect was
catastrophic: in the delta area the dikes broke up at 500 places,
causing 175,000 hectares to be flooded. During the night of the disaster
and the high tide of the next day, Sunday February 1st, 1,835 people
perished, together with tens of thousands head of cattle.
|
|

The
floods on
February 1st, 1953
(source:delta2003.nl)
|
|
The flood disaster of 1953 was the last one in a long series, but it was
also the first one about which the world was notified via the mass
media. In the past the full size and impact of flood disasters hardly
became known among the population in other parts of the country. This
time the public was informed from hour to hour by special editions of
newspapers and radio reports about the events in the disaster area. And
even more impressing were the pictures that were shown in the newsreels
at the cinemas, pictures of flooded towns and villages where boats with
rescue workers sailed down the streets, of people who were plucked off
the roof of their house by a helicopter, and of dead bodies of cows and
horses floating around.
The impact of mass communication was tremendous. Although the 1953
disaster was not by far the hardest ever -the All Saints Flood of 1570
for instance made more than ten times the number of casualties- it raised an
unprecedented spirit of solidarity with the victims, together with a strong feeling of determination to put an end to the constant
threat of the water once and for all now. The statement "This never
again!" was illustrative of the resoluteness that took possession of the
country. Supported by public opinion, politicians and engineers could
start working on the realization of this desire. The result was the
Delta Plan. |
|
|
The Delta Plan
|
|
|
|
The plan that -after several studies- was submitted to parliament for
approval in 1955 was of a simple design but, at the same time, of enormous
proportions. The basic idea was that the safety of the
delta area could be best secured by closing the major inlets
between the islands with dikes that would be strong enough to resist the
heaviest storms. These were -from north to south- the Haringvliet,
Grevelingen, Oosterschelde (Eastern Scheldt), Veerse Gat and
Westerschelde (Western Scheldt).
This concept, which elaborated on plans that were developed before the
Second World War, was quite obvious. Closure of the inlets would reduce
the total length of dikes to be reinforced with no less than 700 km. At
the same time it would create large freshwater reservoirs behind the
dams, which was favorable for agriculture and recreation. And finally
new roads across the dams would improve access to the islands from the
mainland and put an end to their age-long isolation.
|
|

The Delta Plan as it was submitted to parliament
in 1955
(source:delta2003.nl)
|
|
But the realization would be much less simple than it looked at first
sight. There was no expertise at all with closing off estuaries of this
size, where extremely strong tidal currents occur twice a day. However,
the hydraulic engineers were convinced that it could be done. But it
would have a price tag on it of € 900 million, an unimaginable amount of
money at that time. And the realization of the complete plan would take
at least 25 years.
The idea of completely closing off the Western Scheldt was left at an
early stage. International agreements compelled the Netherlands to
guarantee shipping traffic to and from Antwerp an unhindered passage and
with a complete enclosure that would be out of the question. The
alternative was to raise and reinforce all dikes on both sides along the
Western Scheldt. In 1957 the Delta Bill, which settled the realization
and the funding of the Delta Plan was passed, in parliament. So, the work
could now begin.
|
|

The Delta Plan as it was actually realized.
The numbers in the text
refer to this map.
(source:delta2003.nl)
|
|
The first part of the Delta Plan that was to be realized was the
storm surge barrier in the Hollandse IJssel (1), near the town of
Krimpen. The Hollandse IJssel is a modest river that flows into the Maas
just east of Rotterdam. But it runs through one of the lowest areas of
the Netherlands and is a potential safety risk, as at high water levels
related with storm surges the water of the river cannot be drained off
to the sea, threatening the polders along the river that are lying more
than 5 meters below sea level to be flooded.
The safest solution, closing off the Hollandse IJssel completely, was
not an option because of the importance of the river for shipping.
That's why it was decided to build a moveable storm surge barrier, that
would be closed only at extreme high water levels, when there was an
actual risk of flooding. This barrier, which was already completed in
1958, would serve as a model for similar larger-scale constructions in
the Eastern Scheldt and the Nieuwe Waterweg.
|
|

Storm
surge barrier
in the Hollandse IJssel near Krimpen |
|
The next part of the Delta Plan to be realized was the
Drie Eilandenplan (Three Islands Plan) subproject. It contained the
interconnection of the islands of Zuid-Beveland, Walcheren and
Noord-Beveland by closing off the inlets Veerse Gat and Zandkreek. This
would bring the security of the coasts of these three islands to a much
higher level. Additionally, closing off the inlets would gradually
convert them into a large freshwater lake, with new opportunities in the
field of recreation and water management for agricultural purposes.
The
Zandkreek Dam (10) at the eastern side of the project was the first
major enclosure as part of the Delta works and it was an
opportunity for the engineers to gain the experience needed for the much
larger dams that were to follow. The 830 meter-long dam was constructed
upon a backbone of 12 concrete caissons that were sunk down and then
filled with sand. Upon this core the body of the dike was built. The Zandkreek dam was completed in 1960.
|
|

Zandkreek Dam |
|
Next to follow was the
Veerse Gat Dam (8) that was completed in 1961. Its construction was
a new challenge, as the Veerse Gat inlet was more than twice as wide as
the Zandkreek and the tidal currents were much stronger here. To cope
with these currents so-called 'drain caissons' were adopted for the
first time, huge concrete containers of the size of a six-stories
apartment building, with openings so that the water could flow
through unhindered. Only after all caissons had been put in place these openings
were closed by lowering steel slides, closing the whole dam in one go.
Then the caissons were filled with sand and upon this solid core the
body of the dam was built.
|
|

Veerse Gat Dam |
|
After de Veerse Gat Dam the
Grevelingen Dam (5) followed, which links the islands of
Goeree-Overflakkee and Schouwen-Duiveland with each other. With a
projected length of 6 km this dam was considerably longer than anything
that had been built so far. On the other hand this was not a major
seawall but a so-called secondary dam, mainly indented to manage water
flow in the delta area.
For the construction of the Grevelingen Dam three different techniques
were used. The deepest channel, at the Schouwen-Duiveland end, was
closed with caissons similar to those used for the Veerse Gat Dam. To
close the northern channel, which was too wide for the application of
caissons, a special cableway was constructed. Along this cableway cable
cars were running with nets suspended beneath them that were loaded with
rocks and concrete blocks, which were subsequently dumped into the water
at the desired location. The central part of the dam was made by raising
an existing sandbank to the required level with sand. Construction of the Grevelingen Dam started in 1958 and in 1965 it was
ready.
|
|

Grevelingen Dam |
|
The work on building the
Volkerakdam (3) lasted from 1957 till 1969. This was also a seconday
dam, with the main purpose of forcing the water that came pouring in
from the rivers Rhine and Maas into the Haringvliet and then to the
North Sea. As with the Grevelingen Dam an existing sandbar, the
Hellegatsplaat, formed the basis of this causeway. First, the sandbar
was connected to Goeree-Overflakkee by filling the separating channel
with sand. Then the channel between Hellegatsplaat and the mainland of
Noord-Brabant was closed with caissons. Finally the sandbar was linked
to the Zuid-Holland mainland by means of a bridge. On this side the
channel had to remain open to drain off the river water to the
Haringvliet and then to the sea.
On Hellegatsplaat a locks complex was built for the navigation between
Antwerp and Rotterdam, and a motorway junction for road traffic, the
Hellegatsplein. It was a complicated work that took 12 years to
complete. When viewed from the air it looks, with its three 'arms', like
a gigantic Mercedes sign.
|
|

Volkerak Dam
with the traffic junction Hellegatsplein |
|
Work on the
Haringvliet Dam (2) lasted even longer, fourteen years to be
precise, from 1957 till 1971. But we're talking here about one of the
most spectacular parts of the Delta project. A full enclosure was not
possible here as the waters from the Rhine and Maas rivers had to be
drained off to the North Sea via the Haringvliet. The challenge that the
engineers faced was to find a compromise between an open
connection with the sea and a solid seawall. Like the storm surge
barrier in the Hollandse IJssel, but on a much larger scale.
The solution that was chosen was a 4.5 km-long dam in which 17 huge
sluices were incorporated. These sluices are open at low tide, so that
the river water can flow into the sea unhindered. They are closed at
every high tide, to prevent the salt sea water from pouring in. As a
result, the Haringvliet gradually changed into a freshwater lake.
To facilitate the construction of the sluices an temporary polder of
1,400 meter long and 600 meter wide was constructed. On the floor of the
sea the sluices complex was built. After its completion the dike was cut
and the temporary polder was inundated again. Then the work on the dam
itself started. Like with the Grevelingen Dam a cableway was employed to
dump rocks and concrete blocks for the dam into the sea.
In recent years studies have been carried out after the possibility
of leaving the Haringvliet sluices open at high tide too, so that sea
water can pour in again and the former saltwater tidal environment can
-partly- be restored. In that case the Haringvliet Dam will act as a
storm barrier that is closed only at extreme high water levels, just
like the Eastern Scheldt barrier. These studies are still going on. |
|

Haringvliet Dam
|
|
The construction of the
Brouwers Dam (4), closing off the Grevelingen inlet on the North Sea side,
was less complex as it was designed as a solid dam without sluices. As
this inlet had already been closed off by the Grevelingen Dam further
inland it would become a stagnant freshwater lake between the two dams.
With a length of 6.5 km the Brouwers Dam was the longest one built so
far.
For the construction of the Brouwers Dam the same techniques were used
as for the Grevelingen Dam. First, two existing sandbanks, Middelplaat
and Kabbelaarsplaat, were raised with sand and consolidated into
one single artificial island. Then the remaining channels were closed.
For the northern channel 14 'drain caissons' of 68 meters long and 18
meters wide were used; the southern channel was closed by concrete
blocks that were dumped by a cableway.
The work on the Brouwers Dam was finished in 1971. Soon after its
completion massive mortality of flora and fauna occurred in the lake
that used to be the Grevelingen inlet. It has taken quite some time
until a new ecological balance had established itself. Changing views
with regards to nature and environment soon resulted in an adjustment to
the dam. A 195 meter-long sluice was built to allow salt sea water into
the lake and permit fish to swim in and out. This sluice was completed
in 1978.
|
|

Brouwers Dam |
|
After completion of the Brouwers Dam two major challenges remained for the
hydraulic engineers: closure of the Oosterschelde (Eastern
Scheldt) and securing the Nieuwe Waterweg (New Waterway) from Rotterdam
to the sea. A special chapter is dedicated to the Eastern Scheldt
barrier (7), as its history is closely related to the island of Neeltje
Jans. In the case of the Nieuwe Waterweg the challenge was to build a
storm surge barrier that would protect the city and the port of Rotterdam
and the surrounding area against the danger of flooding when
extremely high water levels occur. This is an area where about one
million people are living and with all kinds of vital industrial
complexes like oil refineries, oil storage tank parks and chemical
plants.
The most restrictive factor with designing the barrier was the intensive
shipping traffic in the Nieuwe Waterweg, which is crucial to the
Rotterdam port. A solution like the one in the Eastern Scheldt, with
slides that could be lowered, was not an option here as it would limit
the width of passage and the vertical clearance too much. When opened,
the barrier should obstruct shipping in no way, while in case of
imminent danger it should be possible to close it in just a couple of
hours. It looked like a 'mission impossible'.
The solution was original and unique at the same time. The new
Maeslant barrier (no number on the map) consists of two huge
semicircular and hollow steel doors, which are normally stored in a kind
of dry docks that have been excavated in both shores. In case of acute
danger of flooding water is let into the docks, making the hollow doors to
float. Then the doors are turned outwards, onto the river. When they
are in position against each other, completely blocking the river,
valves are opened so that the hollow doors are filled with water and
sink down onto a specially made threshold at the bottom of the river,
thus forming a solid seawall. When the barrier has to be reopened the
water is pumped out of the doors to make them float again, after which
they are turned back into their normal position in the docks.
Construction of the Maeslant barrier started in 1991 and on the 10th of
May 1997 it was officially put into use by closing and reopening the
huge doors for the first time. Since then the barrier is being tested yearly,
requiring a total suspension of all shipping traffic for about two
hours. But since its commission it has not yet been closed because of
real high water danger. |
|

Maeslant barrier |
The Eastern Scheldt works
|
|
|
|
Though the enclosure of the Eastern Scheldt was not the final part of
the Delta project (the Maeslant barrier in the Nieuwe Waterweg can claim
that honor), it is commonly regarded as the project's pièce de
resistance. Not only because of its sheer size and the innovative
techniques that were used in its construction. But also because it was
the first part of the Delta Project in which nature conservation and
environmental issues influenced the final design in a decisive way.
Already from the start it was clear that closing the Eastern Scheldt
would be the most tricky part of the Delta Project. This inlet was
deeper and wider than all the others and tidal currents here were
stronger and more changeable than elsewhere. That's why this job was
saved for the end, in order to make optimal use of the experience that
had been gained with building the other enclosures. Because of this
delay the environmental movement had the time needed to get organized
against closing off the Eastern Scheldt.
From the viewpoint of nature conservation the Eastern Scheldt is a very
valuable area. The saltwater tidal environment houses an impressive
variety of fish, birds, shellfish and water plants. Additionally,
because of its unique conditions the Eastern Scheldt has become the
cradle of oyster and mussel farming in the Netherlands. All this was
doomed to disappear when the Eastern Scheldt would be closed and change
into a freshwater basin without tidal movement. What happened with the
Grevelingen lake after the completion of the Brouwers Dam in the early
seventies (see above) was brought forward as a warning.
During the entire decade there was a fierce argument going on between
the supporters and the opponents of closing the Eastern Scheldt. An
argument that evolved into a generation conflict, as particularly for
the older people who had personally lived through the flood disaster of
1953 safety and protection against floods was the most important thing,
while for the younger generation nature conservation had the highest
priority. The politicians tried to provide solutions that would meet the
desires of both sides.
|
|
|
|
The first alternative was to raise and reinforce all of the 130 km of
dikes on both shores of the Eastern Scheldt in such a way that the
safety was guaranteed in the same manner as with a total closure, the
method that -from necessity- also was used for the Western Scheldt. The
main trouble with this option was that it would take 20 to 25 years to
bring all dikes to the required standards and this was unacceptable for
those who aimed at maximum safety.
Then several variants for a half open dam were developed, none of which
could find favor in the eyes of both sides. Either the safety could not
be guaranteed sufficiently, or the degree of flow-through was too
little to avoid irreparable damage to the Eastern Scheldt ecosystem.
Then the hydraulic engineers played their final trump: an open multiple
pier dam with floodgates between the piers that could be lowered in case of
storm surge danger. It was a compromise that turned out to be
acceptable for al parties involved.
Construction of a storm surge barrier with movable slides of this size,
in a 'hostile' environment like the unpredictable mouth of the
Eastern Scheldt, would be a hydraulic engineering tour de force that nowhere else in
the world had been done before. It was obvious that this option would
have a price tag on it that was much higher than what had been
estimated for a 'simple' closed dam. The first estimates amounted to €
1.5 billion, which would finally mount to over € 2.5 billion.
The next step was a fierce struggle in government and parliament to get
the required funding for the much more expensive storm surge barrier.
The left-wing parties adhered to the new proposal, but the liberals were
against spending such an amount of money 'just for a couple of birds and
fish'; the Christian Democrats were in doubt. When the latter party came
round in the end and agreed to support the project in 1979, work could begin, at last.
|
|

Storm surge barrier
Eastern Scheldt |
|
Work on the
Eastern Scheldt storm surge barrier (7) started with raising the
existing sandbanks of Roggenplaat, Geul and Neeltje Jans that together would
form the closed part of the barrier, leaving three channels in
which the pier dam was to be built, from north to south the Hammen,
Schaar and Roompot channels. The joint length of the three parts of the
pier dam was 3 kilometer. It would consist of 65 concrete piers, to be
prefabricated in a building dock on Neeltje Jans, with 62 steel
floodgates between them.
A solid and settled subsoil for the piers was of vital importance for
the stability of the whole construction, in an environment where the sea
floor was continuously changing as a result of the strong tidal
currents. If only one of the piers would show a deviation of just a few
centimeters this would irrevocably result in the slides getting jammed,
making the whole barrier completely useless. So, it is obvious that a
lot of effort was put in this particular aspect.
|
|
|
|
First, the seabed was consolidated to a depth of 15 meters. A special
ship was built for this purpose, the Mytilus (mussel), equipped
with 18 meter long vibration pipes with a diameter of over 2 meters,
which were drilled into the soil. The vibrations generated by the pipes
condensed and thus reinforced the subsoil by knocking the sand grains
more closely together. Then, synthetic mats, looking like mattresses
filled with sand and gravel, were laid upon the sea floor. These
prefabricated mats were 200 meters long at a width of 42 meters. To put
these in position another dedicated vessel was built, the Cardium
(cockle). The mats were coiled up in an enormous container that was
fixed to the Cardium, after which the ship sailed to the place of
destination, wound off the mats and laid them down on the seabed at a
speed of 10 meters an hour.
|
|

Mytilus |
|
The 66 piers (including a spare one for the case that something would go
wrong) were built in a building dock on Neeltje Jans, at 15 meters below
sea level. Actually it was a kind of a polder at the bottom of the sea
with a dike around it, that had been drained by pumping out all the
water. The piers themselves were gigantic, partly hollow concrete
constructions that varied in height between 30 and 38 meters, depending
on the position where they had to be placed.
When the piers were completed the dike around the building dock was cut
and the site was flooded. To transport the piers to their final
destination again a special ship was built, the Ostrea (oyster).
This U-shaped vessel maneuvered itself around a pier with the open side
of the 'U', after which two 50 meter high porches lifted the monster
with a weight of 18,000 tons off the sea floor.
|
|

Cardium |
|
This way, each of the piers was transported to its place of destination,
where another specially designed positioning vessel, the Macoma
(nun) was anchored at the exact location for the pier to be placed. The
Ostrea was coupled to the Macoma to provide for the
necessary stability to place the pier with great precision on the sea
floor. When the pier was in place its hollow interior was filled
with sand to increase stability. To protect the base of the pier it was
wrapped with thousands of tons of rock.
When all 63 piers stood firmly on the sea floor (the spare pier turned
out to be redundant), the most critical part of the job was done. Now
the piers were raised to the required height with concrete top pieces
and joint together by means of hollow tubes that were to house the
equipment for moving the slides. On top of these tubes the roadway that
runs along the barrier was built. Then the 62 steel floodgates were put
into place by a crane. Their sizes vary, depending on the size of the
opening that they have to close off. The biggest one is 12 meters high
at a weight of 480 tons.
Eventually, the Eastern Scheldt storm surge barrier was officially
opened on 4 October 1986 by HM Queen Beatrix.
|
|

Ostrea |
|

Macoma |
|
In conjunction with the construction of the Eastern Scheldt barrier some
additional works were performed that initially had not been incorporated in the
Delta Plan, but turned out to be necessary when it was decided to keep
the Eastern Scheldt open. They are referred to as the 'compartment
works', as in a certain sense they divide the Eastern Scheldt in separate
'compartments'. The most important ones are the Oester Dam and the
Philips Dam.
As a result of the building of the storm surge barrier the mouth of the
Eastern Scheldt was narrowed considerably. Less water could flow in and
out than before, reducing the tidal movement with about one quarter. To
neutralize this effect it was decided to effectively reduce the area of
the Eastern Scheldt by building extra dams at the eastern end. This
would increase high-water levels in the Eastern Scheldt with about 3
meters.
The 'compartment works' also solved an additional problem. The new
Scheldt-Rhine Canal that was being built, linking the ports of Antwerp
and Rotterdam, was projected partly through the Eastern Scheldt and thus
would be subject to tidal movement. By separating the easternmost part
of the Eastern Scheldt from the open part with a dam the whole
Scheldt-Rhine Link would become 'non-tidal' and have a constant water
level, so that no additional locks would be necessary.
|
|
|
|
First, the
Philips Dam (6) was constructed between 1977 and 1987, a new branch
of the Grevelingen Dam to the former island of Sint Philipsland,
separating the Eastern Scheldt from the waters of the Krammer and the
Volkerak. A locks complex was included in this dam, to enable shipping
traffic in and out of the Eastern Scheldt. For building the locks an
artificial island was constructed on an existing sandbank, the Plaat van
Vliet. The
Krammer Locks use a highly sophisticated system for separating salt
and fresh water; more details about this can be read on the
Sint Philipsland page. After the
completion of the Philips Dam the area of the Eastern Scheldt had been
reduced with 3,500 hectares of water.
|
|

Philips Dam
with the
Krammer Locks |
|
Now still remained the construction of the
Oester Dam (11) between the (former) islands of Tholen and
Zuid-Beveland, reducing the Eastern Scheldt area with another 1,000
hectares of water. Although this part of the Delta Works is less
widely known it is certainly not the least one; on the contrary, with a
total length of 11 kilometer the Oester Dam is even the longest one in
the whole project. Construction work started as early as 1979 and ten
years later the dam was officially opened. For closing the final opening
in 1986 the gates of the brand new Eastern Scheldt barrier, which was
not even officially put into use at that time yet, were closed to reduce
the tidal currents in the Eastern Scheldt. The water east of the Oester
Dam now forms a 'non-tidal' freshwater lake, which has improved water
management in the westerly part of Noord-Brabant considerably.
|
|

Oester
(Oyster) Dam |
|
With the opening of the Maeslant barrier on 10 May 1997 the Delta Works
have been formally completed. Dutch coastal defense is now capable to
withstand high water levels that statistically will occur only once in
4,000 years. From far and near visitors now come to Neeltje Jans and the
other Delta Works to see how the Dutch have finally conquered the sea.
Many of them coming from the United States nowadays, after the
devastating floods that were caused by the hurricane Katrina over there
in the New Orleans area recently.
So, can we lean back comfortably for the next 4,000 years? Definitely
not! In the first place because that fatal storm surge might equally
well occur tomorrow than only in 2,000 years. And secondly because that
so-called Delta Standard is already being questioned, only half a
century after it was adopted. Recently gathered knowledge about changes
in our climate make believe that, as a result of the rise of the sea
level and more frequent occurrence of extremely heavy storms caused by
global warming, it might take much less than 4,000 years before a new
Delta Plan needs to be developed. In fact, work on it has already begun! |
|
|
|
A visit to Neeltje Jans
|
|
|
|
The major reason to visit Neeltje Jans is to get a comprehensive view of
the Delta Project in general, and the Eastern Scheldt storm surge
barrier in particular. Don't expect much more of interest on this raised
sandbank and former building dock. This in spite of attempts by Rijkswaterstaat (the
Department of Public Works) to stimulate the formation of
dunes here in order create some more interesting nature, with the
unexpected result of a rabbit plague on the island! Pure nature can
certainly
be found on the beach at the North Sea side, where you are allowed to
get rid of all of your clothes if you want, as it is an official nudist beach.
But impressive as they are, the Delta Works form a rather technical
theme and for that reason they are possibly not attractive enough to
justify a holiday
trip with the whole family. That's the reason why the former information
and exhibition center Delta Expo was transformed in 1997 into the theme
park WaterLand
Neeltje Jans, with many attractions for young and old like an
aquarium, a hurricane simulator, water chutes, a beach playground, a seals show and much
more. Besides that there are frequently special temporary events, like a sand
sculpture festival and the exhibition 'Dynamic Art Delta', both in the
summer of 2005.
|
|

Neeltje Jans
in Google Earth
(click to enlarge) |
|
 |
|
<
click on an image to enlarge |
|
|
|
|
|
 |
|
The ride to Neeltje Jans across the storm surge barrier is certainly
impressive, particularly if you are approaching the former sandbank from
the north. You are crossing the first two channels in the Eastern
Scheldt, Hammen and Schaar, which gives you a good impression of the
barrier's size. During its construction a 4 km-long temporary steel
bridge was lying here, to enable the hundreds of workers on the project to get to and
from Neeltje Jans. |
|
|

Construction of the temporary bridge
to Neeltje Jans in 1979
(Source: Rijkswaterstaat) |
|
A good start of a visit to Neeltje Jans is the film showing
'Delta-Finale' at the exhibition center (several different language
versions available). It gives a lot of background information about the
flood disaster of 1953, the development of the Delta Plan and the
realization of the project. In particular the construction of the
Eastern Scheldt storm surge barrier is highlighted, as this work is
commonly considered to be the final of the Delta Works. You will get an
overall view of the technical challenges that had to be met and the
sometimes unconventional solutions that had to be invented as an
hydraulic engineering work of this size never had been done before. Also the various
special vessels that were purpose-built for the barrier are highlighted.
But at least as much attention is paid to the change of public feeling
that occurred during the realization of the Delta Plan, in favor of
ecology and nature conservation. Without that change of mind the storm
surge barrier would not have been built at all and the Eastern Scheldt
would have been closed by a solid dam as originally planned. Perhaps
that aspect of the barrier is even more fascinating than all those
technical fireworks; the fact that all of this effort was made just to
conserve a piece of unique nature that would have been lost otherwise.
|
|
|
After the film and a brief visit to the exhibition in
the brand new Delta Plaza building (the previous one was
completely destroyed by a fire in 2002) you walk via the
outdoor exhibition area, where several tools that were
used during the construction of the storm surge barrier
can be found, to the barrier itself. The first segments
of its central part, between the islands of Neeltje Jans
and Roggenplaat, are open to the public. |
|
 |
|
|
|
|
Along concrete stairs you descend into the interior of one of the piers
and shortly after you find yourself standing on the upper girder of the
barrier, right beside one of the immense steel floodgates weighing over
400,000 kilo, while below you the waters of the Eastern Scheldt are
swirling. You walk along the lifting portals with the huge hydraulic
cylinders that move the gates, controlled from the 'Topshuis' building
across the road, which was named after J.W. Tops B Sc, director-general
of Rijkswaterstaat who died in 1981.
On one of the piers a thick red line marks the water level, +3 meter MSL,
at which the 62 slides of the barrier will be closed, fully automatic
and computer controlled. A thinner red line marks the maximum water
level that was reached during the 1953 disaster, +4,20 meter MSL. A
level that -still- has not been matched since then.
|
|
|
|
|
|
|
|
From the Eastern Scheldt barrier you walk along the remains of what once
was the surrounding dike of the construction dock back towards the
exhibition building Delta Plaza. I remember that I have been here
before, in the early 1980s, when the barrier was still under
construction. Neeltje Jans was open to the public by then, though, but
you were not allowed to walk around there on your own as that was too
risky. From Schouwen-Duiveland a shuttle bus brought the visitors across
the temporary bridge to the information center on the artificial island,
which was housed in a modest wooden shed at that time.
|
|
|
|
 |
|
From this same dike, where now a tractor-pulled tourist park train
rides, you had a spectacular view of the construction site at the bottom
of the Eastern Scheldt, 15 meters below. There the piers for the storm
surge barrier stood, in various stages of construction, neatly lined up.
It is still visible that the building dock was divided in four separate
parts by secondary dikes, so that it could be inundated again partially. |
|
|

Piers under
construction
(Source: Rijkswaterstaat) |
|
This way the first piers that were already finished
could be transported to their destination while work on
the other ones was still going on. The highlight of the
trip to Neeltje Jans by then was a bus ride down into
the building dock, closely past the piers that were
under construction. Only there you could be really
impressed by the huge dimensions of these concrete
giants, of which nowadays only the small part rising
above the water is visible. |
|
 |
|
|
|
|
|
|
|
|
 |
|
When you look today across the water towards the recreation beach and
the exhibition building Delta Plaza, there is nothing left that reminds
of those days. Or is there something yet? In a corner of the former
building dock the spare pier is still standing at the place where it was
built, the 66th pier that was never collected by the Ostrea
because it wasn't needed anymore. Its construction wasn't all useless as
it now acts as a popular object for climbing. |
|
|
|
|
Walking back to Delta Plaza along the other side of the water you are
passing the hurricane simulator, one of the most popular attractions of
WaterLand Neeltje Jans. Huge fans can generate wind speeds of over 100
km per hour, wind force 12 on the Beaufort scale. Meteorologists then
speak of a hurricane. Equipped with (mandatory) safety glasses you can experience
personally what that feels like. A very special sensation that you will
hopefully not undergo too often in the open air!
Somewhat beyond is the exhibition
Walviswereld
(Whale World) where children can learn everything about whales. It is
housed in a building of futuristic design that looks like a huge shining
whale and that has won several awards, including the first Architecture
Award of Zeeland. Inside you imagine yourself in the gloomy bowels
of a real whale.
During my most recent visit to Neeltje Jans in July 2005 several art
objects were set up along the promenade walk. They were part of the art
event 'Dynamic
Art Delta' that took place on the island from May till October.
Specially for this exhibition eight artists from Belgium, Germany and the Netherlands
designed ten compositions related with wind, water and nature. Most of these were so-called 'kinetic objects', which
means that they are set in motion by natural forces like wind or
streaming water. These objects provided a pleasant and delicate
compensation for all of the massive and impressive concrete and steel of
the Delta Works!
|
|
|
|
Doorkijk naar... (View through...) is made by the
German-born artist Paul Kamper (1926) and aims at the
horizon. "Our expedition into space starts with the
desire to know what is behind the horizon. Seven
reflecting rings that are suspended in line one behind
the other are forcing your view into the distance. At the
same time, the mirrors reflect that what's behind you.
This way past, present and future are brought together." |
|
 |
|
|
|
|
|
|
|
|
 |
|
WWV 233 by Michael Hischer (Germany, 1955).
"A sculpture that moves gets an extra dimension, it
acts as it were. It is no longer a thing but it looks like a person.
WWV 233's arms move separately, giving the sculpture the capability
of adopting an unlimited number of shapes. One of the aspects of my work
is the visualization of time by movement, so that you can experience
time physically as well as mentally." |
|
|
|
|
|
|
|
|
WindZug (WindTrain) by Bernward Frank (Germany,
1959). "A coil runs on two aluminum cones along a
circular track like a train on the rails. Merely by the
shape of the cones the coil can remain in its track
without any additional guidance. Together with the sound
that is produced by the movement it provides a
fascinating spectacle. Although I prefer massive,
monumental shapes in my work, just a slight breeze is
enough to set something in motion." |
|
 |
|
|
|
|
|
|
|
|
 |
|
Anatomy of Ecstasy by Raphael Opstaele (Belgium, 1934) consists
of three spacecrafts. "They offer you a trip to a place for which no
words exist yet. Interchanges with the 'OUTSIDE WORLD' are of major
importance for our further intellectual development. Man is already
living in seclusion for too long, causing him to become sterile and
unable to feel the 'sacral vibrations' from the 'UNIVERSE' like our
ancestors could." |
|
|
|
|
|
|
|
|
Leve de Koningin! (Long live the Queen!) by Albert in 't Veld
(Netherlands, 1942) is inspired by Queen Beatrix' 25-year's
jubilee. "On top of the brightly painted rods you see
the Queen's portrait in forty fold, like an iron lady
cut out by a laser technique. As some parts have been
left open, light shines through her face. It is
obvious that waving hands must also be included in a
sculpture like this. The wind causes the steel rods
to move gently." |
|
 |
|
|
|
|
|
|
|
|
At the end of my walk round I arrive at the recreation beach, where at
the time of my visit people were working hard on the completion of the
sand sculptures that could be admired here during the months July and
August. For me it meant a renewed acquaintance with Nehalennia, as the
patroness of the seamen from the Roman ages, who lent her name to the
island of Neeltje Jans, formed the central subject of this event.
The seven several meters high sand sculptures were not yet completely
finished. On the 1st of July the exhibition was to be officially opened
by Miranda Slabber, the Zeeland-born Miss Holland 2004. In the
sculptures themes like the construction of a temple, merchants making a
sacrifice, Romans worshipping the goddess and also the decay of the
Nehalennia cult were depicted.
The sand sculptures were being built by INAXI, a Dutch company with an
internationally renowned team that also works frequently in China,
Israel and Germany. This team is holder of the world record of the tallest
sand sculpture, 21 meters high. Special sculpture sand is used, which is
being pounded in moulds and then transported to the building site in the
form of blocks, where the sand sculptors or 'carvers' make the rough
shapes by cutting away the sand. Then the sculptures are being
elaborated in detail.
|
|
|
|
|
|
|
|
With a very last look at the astonishingly detailed sand sculptures my
brief tour around Neeltje Jans comes to an end. I leave this place with
mixed feelings. Not because it wasn't a rewarding visit, on the
contrary. For everyone who is interested in the struggle of the Dutch
against the water and how they have succeeded in keeping up with it in
recent years Neeltje Jans is definitely a must. In particular for
foreigners who are not familiar with the Dutch way of 'living below sea
level' there is no better place to get acquainted with it and to become
impressed by the Dutch hydraulic engineering skills. And certainly now
that there are more than enough attractions for children and for those
with less interest in technical details Neeltje Jans is an good
idea for a day trip with the whole family.
But on the other hand, to say that I have experienced the slightest 'island feeling'
would be far too much. There is nothing wrong with its location, in the
middle of the Eastern Scheldt, with plenty of light and room around.
That's great, but not enough to make a place a real island.
That requires people in particular, people who have lived there for
generations, isolated from the mainland and completely left to their own
devices. People who, even if they have abandoned the place since long, have
left their marks on the scenery, something of their own that still can
be sensed after all those years.
On Neeltje Jans nothing of that is tangible. It just remains a heap of
sand in an estuary, that appeared on the maps only in the 18th century
and that accidentally came in handy for the construction of one of the
largest hydraulic engineering works in the world. It's nothing more than
that. But nothing less too!
|
|
|
|
 |
|
|
|
|
|
|
|
More about Neeltje Jans and related information
|
|
|
|
www.neeltjejans.nl
Official website of theme park WaterLand Neeltje Jans.
Dutch, German and English language versions available.
www.deltawerken.com
Website about the Delta Project by the Delta Works Foundation Online. Dutch and English versions.
www.delta2003.nl
Official website of the Project Delta 2003, the commemoration of
the flood disaster of 1953. Dutch and English language.
www.zeeuwsarchief.nl/strijdtegenhetwater
Website of the Rijksarchief (Dutch National Archives) about the
flood disaster of 1953 and the Delta Works. Dutch language only.
www.walviswereld.nl
Website van the attraction 'WalvisWereld' ('Whale World') at WaterLand Neeltje Jans.
Dutch language only
www.cedephoto.com/dad2005
Website of the art event 'Dynamic Art Delta'. English language only.
www.zeeland.nl
Official website of the Province of Zeeland, to which
Zuid-Beveland belongs. Dutch language, with some content in
English, French and German.
|
|
|
|
June
2005
|
|
|
|
|
|